Tesla Delays Optimus External Deliveries to Late 2027 Amid Hardware Hurdles

The automator pushed its humanoid robot rollout back by nearly two years, citing persistent issues with the robot's hands and durability despite claims of competitive dominance.

By Kwame Barrett ·

Illustration for: Tesla Delays Optimus External Deliveries to Late 2027 Amid Hardware Hurdles
Illustration generated for this article, not a news photograph.

The timeline for Tesla’s humanoid robot has slipped again, leaving investors and industry watchers to wonder if the company’s ambitious projections will ever align with reality. On the Q3 2026 earnings call, CEO Elon Musk confirmed that external deliveries of the Optimus robot are now targeted for the end of 2027. This marks a significant delay from earlier promises, as the company identifies the robot’s hands, overall durability, and artificial intelligence as critical areas requiring further development before the machines can be sold to outside firms.

The production infrastructure is already in place, but the output remains far below potential. Tesla has installed the majority of a high-volume line in Fremont, originally built for Model S and X vehicles, designed to eventually produce around 20,000 units weekly. However, Musk acknowledged that reaching this capacity will take at least a year, possibly longer, due to ongoing design changes. The company has only recently begun early production, and the transition from prototype to mass manufacturing is proving complex.

The core technical challenge lies in the hardware, specifically the robot’s hands. During the call, a Tesla engineer highlighted the hand as one of the most difficult hardware components, alongside custom gears that face reliability concerns. Musk agreed, explaining that the fingers must be soft enough to handle delicate objects yet durable enough to withstand constant wear, a challenge complicated by the fact that robots cannot heal like human skin. This mechanical complexity is a primary factor in the delayed timeline.

On the software front, Tesla is grappling with AI architecture issues. Unlike its vehicles, which have a massive fleet collecting data for Full Self-Driving, Tesla lacks a comparable data stream for robots. To address this, the company plans to build 10,000 to 20,000 robots that will practice tasks in an "Optimus Academy." Additionally, the company intends to integrate its AI5 chip into the robots around April 2027. Musk promised a video demonstration within one or two months showing the robot performing unscripted tasks, arguing that many current industry demos are merely pre-programmed routines.

This delay follows a history of shifting deadlines. In 2024, Musk suggested internal use in 2025 and high-volume external production in 2026. By January 2025, he projected 10,000 robots built that year, with several thousand performing useful work by year’s end; he later admitted that none had achieved this. Tesla’s own Q3 shareholder letter now describes the current output as the first "production-quality" units, implying that previous iterations did not meet the company's internal standards. Reports from last month indicated that the hand and forearm contained over 100 small parts assembled by hand, with touch sensors facing reliability issues.

Musk’s claim that no competitor is "even close" to Tesla’s progress invites scrutiny from rivals who have made tangible advances. XPeng, for instance, activated an automated production line for its IRON robot in Guangzhou in September, with over 80% of core processes automated. XPeng targets mass production by the end of 2026 and deliveries in the first half of 2027, a timeline similar to, if not slightly ahead of, Tesla’s. Meanwhile, Boston Dynamics has begun producing its electric Atlas robot and has committed all its 2026 deployments, including to Google DeepMind. Hyundai plans to deploy 25,000 robots across its plants in the coming years.

The competitive landscape suggests that Tesla is not operating in a vacuum. Boston Dynamics took a pragmatic approach to the hand problem by prioritizing sturdy grippers for industrial use over human-like dexterity, effectively bypassing the specific hurdle Tesla cites as its main obstacle. The company also hired Milan Kovac, Tesla’s former head of Optimus, in January. While Tesla may have built the most robots to date, the challenge now is making them useful and reliable enough to justify their cost in industrial settings.

As the industry moves forward, the stakes are high for Tesla to prove its technology is viable. The company faces the same fundamental problems as its competitors: creating hands that survive real-world work, ensuring reliability, and developing AI that can generalize to new tasks. With electricity rates rising and the demand for automation growing, the pressure on these companies to deliver functional, cost-effective robots is intensifying. Whether late 2027 will mark a true breakthrough or just another milestone in a recurring pattern of delays remains to be seen.

Source: Electrek · original report published

More Tech · Report a business · Got a Story?

Get True Media Now in your inboxBig-city news, all in one place. Free, a few times a week, unsubscribe any time.

Get True Media Now in your inboxBig-city news, all in one place. Free, a few times a week, unsubscribe any time.